Hai everyone!
I have an issue about planning in AX 12 Feature Pack.
I have an item finish good (FG) with raw material A size 1 with qty 100, and raw material A size 2 with qty 100
When I create plan order or run master/forecast scheduling to item FG, system create two plan purchase order to item A size 1 only, with qty 100 and 100.
Why does system not create plan order based on FG BOM?
System should have created plan purchase order for item A size 1 and A size 2, with qty 100.
This miscalculation plan also happened with other variance, such as configuration and color.
I very apreciate all help
Hendrianto,