Quantcast
Channel: Dynamics User Group
Viewing all articles
Browse latest Browse all 15740

Operation scheduling

$
0
0

Hello everybody, I have a situation where I'm running master scheduling, and I have configured the system to plan for capacity also for planned orders, my default method is Operation scheduling.

I have a Resource group EM01 which has 5 resources, each one has 18hs of capacity per day, the whole group would be 90hs/day (18hs * 5 resources).

I have entered a sales order for an item, requirement date Jun-15, the quantity based on the route will consume a whole day of EM01 operation, working with the 5 resources.

When running master planning, it is showing in the capacity load for the group, that only 18hs are used per day from today Jun-11, as if I was going to use only one resource per day, on Jun-15 I will be used the 90hs and have the production finished. But I want to see, that the whole production is made on one day, using full capacity on Jun-14.

What should I do to achieve this?

Thanks!


Viewing all articles
Browse latest Browse all 15740

Trending Articles